Free PMI-ACP Actual Exam Questions - Question 13 Discussion
experienced pool of agile team members from a previous project, as well as a pool of available
internal team members with some Scrum background.
What should be considered when selecting the team?
Probably B. It’s smart to have a mix of experts and generalists to handle different parts of the project and figure out where training might be needed early on.
Option B definitely covers more bases than just picking top performers or eliminating based on conflicts. It’s about balancing skills and spotting training needs, which feels more practical for a fresh project.
B. It's important to mix experts with well-rounded team members to cover all project needs and spot where training is needed, rather than just picking high performers or focusing only on past conflicts.
Maybe D could work too since knowing who performed well before might help predict who can contribute most in the new Scrum team. But it ignores team chemistry and learning potential.
Maybe B, mixing experts and broader experience sounds practical for skills and training.
Option B sounds right here because balancing experts and those with some experience usually helps cover skill gaps and keeps the team flexible.