Free CompTIA Project+ PK0-005 Actual Exam Questions - Question 15 Discussion

Question No. 15
When creating a project schedule, a project manager adds activities with zero duration. Which of the
following describes these types of activities?
Select one option, then reveal solution.
US
AV
Amit V.
2026-02-21

I agree it’s likely C, since milestones mark important points without time attached. D doesn’t fit because a work breakdown structure is about hierarchy, not activity duration. Could the question be tricking us with terminology?

0
AV
Amit V.
2026-02-16

Not A, critical paths are the longest sequence of activities, so they definitely have duration. Milestones (C) make more sense since they're markers with no time assigned.

0
PO
Peter O.
2026-02-14

It’s C. Milestones mark key points, not actual work, so they don’t take time. The other options either relate to paths, resources, or structure, not zero-duration events.

0
CA
Chris A.
2026-02-01

C imo, milestones signal key points without consuming time.

0
CA
Chris A.
2026-02-01

C, milestones are definitely zero duration markers in schedules.

0
PA
Peter A.
2026-01-29

Maybe C, since activities with zero duration usually mark significant points or decisions, not actual work. Critical paths and resources definitely involve time or effort, so they don’t fit here.

0
PA
Peter A.
2026-01-28

C/D? Milestones fit zero duration, but work breakdown structures are more about task grouping.

0
ZT
Zain T.
2026-01-26

That’s definitely C; milestones are just markers for key events without any time needed. None of the other options fit since resources and work breakdown structures aren’t about duration.

0
ZT
Zain T.
2026-01-22

It’s C because milestones mark points, not tasks with time.

0
AS
Ali S.
2026-01-15

It’s C. But does zero duration always mean a milestone here?

0