Free CompTIA Project+ PK0-005 Actual Exam Questions - Question 1 Discussion
SIMULATION During a gate review meeting, the deliverable was rejected by the customer. INSTRUCTIONS Review the dashboard. • Part 1: Drag and drop each task, placing them in the correct order based on the project change control process. • Part 2: Select the proper document(s) to be updated. If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

The order starts with identifying the change, then impact assessment, approval, and finally updating relevant documents.
I’d say the key is to do the impact assessment first to understand the change’s effect, then get formal approval. Only after approval should you update the change request and any related docs like the project plan.
consider getting formal approval for the change request before updating any documents. Skipping approval could cause confusion later on. So, the sequence should be impact assessment, approval, then update the change request and project plan.
Agree with starting on impact assessment to know what’s changed. But I’d say the change request form or log needs updating right after approval, not just after assessing impact. Keeps everything official.
I think the first step should definitely be assessing the impact of the rejection to understand how it affects scope, schedule, or cost. Without that, it’s hard to know what needs changing. After that, it makes sense to get formal approval on the next steps because you don’t want to update any project documents before everyone agrees on how to handle the rejection. Finally, once you have approval, you update the relevant docs like the project plan or schedule. Doing this out of order risks rework and confusion. So the order is impact assessment → approval → documentation updates.
I’d add that documenting the rejection itself should happen immediately after impact assessment to keep a clear record.
I’d say after assessing the impact, the next step should be to notify stakeholders for approval, so you’re not updating docs prematurely. Only after formal approval do you update key documents like the project plan or schedule.
I agree with starting by assessing the impact to know exactly what changed. Then, approval is key before updating anything to avoid unnecessary work on documentation that might be rejected again.
I think you should first assess the impact of the rejection, then get approval on how to proceed before updating any documents. Updating docs too early might cause confusion if the changes aren't approved yet.
Start with impact assessment makes sense, then approval before any doc updates.
Start with identifying impact, then get approval before updating docs.
This simulation feels tricky 'cause the steps aren’t super clear. The ordering seems important, but I’m not sure if they want all documents updated or just specific ones after rejection.