Free US Green Building Council LEED AP O+M Actual Exam Questions
The questions for this exam were last updated on January 7, 2026
Dumps Box (DumpsBox) offers up-to-date practice exam questions for LEED AP O+M certification exam which are developed and validated by US Green Building Council subject domain experts certified in US Green Building Council LEED AP O+M . These practice questions are update regularly as we keep an eye on any recent changes in LEED AP O+M syllabus, and when there is update our team quickly adjusts the questions. This commitment to providing the best quality exam prep material to certification aspirants is what makes DumpsBox.com the best certification exam prep website. On top of that, our strong, yet strictly moderated, community based feedback keeps the content clean and current. Each question has helpful community discussion that provides it extra perspective and introduces helpful resources for better exam preparation. This also saves students from other outdated practice questions or illicit exam dumps that can have adverse affects on career. Browse through our US Green Building Council LEED AP O+M exam questions and pass your exam on first try.
For an office building with few visitors, which of the following actions must the project team do in order to comply with Location and Transportation Credit, Alternative Transportation?
Select one option, then reveal solution.
Question No. 2
Which of the following is the most appropriate use of untreated stormwater?
Select one option, then reveal solution.
Question No. 3
How is the energy baseline determined in Minimum Energy Performance if the building type is not addressed by the ENERGY STAR® rating tool?
Select one option, then reveal solution.
Question No. 4
An ASHRAE Level 1 walkthrough analysis contributes to what prerequisite or credit?
Select one option, then reveal solution.
Question No. 5
Under Indoor Environmental Quality Credit, Interior Lighting, outlet powered task lighting contributes towards compliance for what category of building space?
Select one option, then reveal solution.
Question No. 6
A 1,500 ft2 (139 m2) mobile home is built in the downtown area of a major city. 90% of the project's gross floor will be completed by the time of occupancy. LEED certification is being sought. Which rating system would be the most appropriate one to use?
Select one option, then reveal solution.
Question No. 7
What percentage of individual occupant spaces must have individual lighting controls in projects seeking Option 1. Lighting Control in Indoor Environmental Quality Credit, Interior Lighting?
Select one option, then reveal solution.
Question No. 8
The Materials and Resources (MR) section includes which of the following building products in Credit calculations?
Select one option, then reveal solution.
Question No. 9
The minimum amount of renovation or new construction work required to qualify for Materials and Resources Credit, Purchasing - Facility Maintenance and Renovations is
Select one option, then reveal solution.
Question No. 10
Key functional and operational parameters such as occupied hours of a building, use by space type, required temperature settings, and lighting levels, are specified in the
Select one option, then reveal solution.
Question No. 11
Which of the following best meets requirements of Sustainable Sites Credit, Site Development - Protect or Restore Habitat?
Select one option, then reveal solution.
Question No. 12
The project team is attempting to achieve Option 1. Lighting Controls in Indoor Environmental Quality Credit, Interior Lighting. Which of the following is required documentation?
Select one option, then reveal solution.
Question No. 13
What must the project team do in order to maximize the reduction in operational costs with regard to Sustainable Sites Credit, Site Improvement Plan?
Select one option, then reveal solution.
Question No. 14
What is the maximum distance between readings required to represent the illumination levels at the property perimeter to earn the Sustainable Sites Credit, Light Pollution Reduction?
Select one option, then reveal solution.
Question No. 15
A district energy system provides chilled and hot water to a building on a campus. What equipment must be commissioned to meet the requirements of Energy and Atmosphere Credit, Existing Building Commissioning - Analysis, Option 1. Existing Building Commissioning?