Free Scrum PSM I Actual Exam Questions - Question 7 Discussion
integrated every Sprint?
Option B, because integrated increments give a clearer, collective view for all stakeholders.
B. Integrating every Sprint keeps the product in a usable state and helps catch issues early, which fits Scrum’s focus on transparency and inspection. Waiting or skipping can create hidden problems later.
A/D? A seems practical, only integrating when dependencies actually exist might save unnecessary work for independent teams. D feels off since the whole idea of Scrum is to avoid hardening Sprints and keep continuous integration. B sounds good but assuming every team’s work must be integrated regardless might be overkill if some teams really are working completely independent parts. So A feels like a more balanced answer here considering real-world team dynamics.
A/C? I get why B sounds right, but A says integration is only needed when dependencies exist, which might save time for independent teams. C feels off since Scrum encourages collaboration.
B. Even if some teams don’t have direct dependencies, integrating increments every Sprint helps avoid surprises and technical debt piling up. Waiting longer to integrate can cause messy conflicts and slow down delivery. So it’s more about keeping everything transparent and manageable, not just for complex products but any product with multiple teams.
This one feels pretty clear to me. Each team’s work should come together every Sprint so stakeholders can see real progress, so I’d go with B.