Dumps Box (DumpsBox) offers up-to-date practice exam questions for PMI-SP certification exam which are developed and validated by PMI subject domain experts certified in PMI-SP . These practice questions are update regularly as we keep an eye on any recent changes in PMI-SP syllabus, and when there is update our team quickly adjusts the questions. This commitment to providing the best quality exam prep material to certification aspirants is what makes DumpsBox.com the best certification exam prep website. On top of that, our strong, yet strictly moderated, community based feedback keeps the content clean and current. Each question has helpful community discussion that provides it extra perspective and introduces helpful resources for better exam preparation. This also saves students from other outdated practice questions or illicit exam dumps that can have adverse affects on career. Browse through our PMI-SP exam questions and pass your exam on first try.

Question No. 1
Examine the figure given below:
PMI-SP practice exam questions
If Activity B takes eight days to complete instead of five days as schedule, how long can you now
delay Activity H?
Select one option, then reveal solution.
Question No. 2

Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

Select all that apply, then reveal solution.
Question No. 3
You are the project manager for your company. You are working with the activities defined in the
figure below.
PMI-SP practice exam questions
What will happen to your project if Activity F takes five additional days to complete than what was
expected?
Select one option, then reveal solution.
Question No. 4
You are the project manager of the GHT Project. Ben, one of your project team members, does not
understand the idea of a milestone. Which of the following best describes what a milestone is?
Select one option, then reveal solution.
Question No. 5
Harry works as a project manager for BlueWell Inc. He is determining the budget of the project.
According to the PMBOK, there are seven
inputs to this process. Which one of the following is NOT an input to the determine budget process?
Select one option, then reveal solution.
Question No. 6
Holly is the project manager for her organization. In her project, she has worked with the project
team to define when the project team will be utilized in the project, the duration of the project
activities, and the sequence in which the project work must be completed. During several phases of
her project, the project team will need to work more than fifty hours per week. The project team
members have agreed this is necessary and they're willing to do the work to complete the project.
Management, however, has not approved Holly's schedule based on the overtime the scheduling
will require. They have set a limit on the project schedule of 45 hours per week. What is this limit
technically called? Each correct answer represents a complete solution. Choose all that apply.
Select all that apply, then reveal solution.
Question No. 7
Joe is the project manager of the HJN Project. Joe's project is a renovation of an office building.
There must be 30 hours between the painting activity and the carpet activity in the project schedule
to eliminate the risk of wet paint getting on the carpet. What is the best approach Joe can do to
alleviate this issue?
Select one option, then reveal solution.
Question No. 8
The Define Activities process is the first process in the project time management knowledge are
a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave
planning, templates, and expert judgment. Which one of the following is not an output of the Define
Activities process?
Select one option, then reveal solution.
Question No. 9
You are the project manager for your organization. You are meeting with your customers to discuss
the project performance. In this meeting, you will have eight project customers, the project sponsor,
and ten members of your project team. What type of communication method are you using in this
instance?
Select one option, then reveal solution.
Question No. 10
You work as a project manager for BlueWell Inc. Which of the following tools/techniques will you
use to demonstrate how a process behaves over time, and when a process is subject to special cause
variation, resulting in an out-of-control condition?
Select one option, then reveal solution.
Question No. 11
Vicky is the project sponsor of Robert's project. She has requested several changes for the project
scope and these changes have, of course, been approved. Robert needs to incorporate the project
scope changes into the activity list. Where else should Robert reflect these project changes?
Select one option, then reveal solution.
Question No. 12
You have been hired as a contract project manager for Tech Perfect Inc. The project has already been
started. Sufficient details of the project have already been structured. You are working with your
team for cost estimation of the project. Which of the following estimating techniques will you use
for the highest degree of accuracy?
Select one option, then reveal solution.
Question No. 13
Joseph works as the project manager of the NHQ Project. He has created the project network
diagram as shown in the figure:
PMI-SP practice exam questions
Based on the network diagram, find out which path is the critical path for this project?
Select one option, then reveal solution.
Question No. 14
Which of the following techniques is used in businesses to determine the effect different costs or
investments have on profit and other financial indicators?
Select one option, then reveal solution.
Question No. 15
Gary is the project manager of the GHY project. He has elected to use a previous, but similar, project
to guide him and the project team through the estimate activity duration process. The previous
project schedule could best described as which one of the following?
Select one option, then reveal solution.