Free PMI PMI-RMP Actual Exam Questions - Question 8 Discussion

Question No. 8
During a risk identification process in a construction project, the lack of space to install air
conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?
Select one option, then reveal solution.
US
MR
Marco R.
2026-02-17

It’s C because a time delay during installation signals a problem early in the process, before quality issues or bigger disruptions happen. The others are more about potential or later-stage issues.

0
AW
Ahmed W.
2026-02-17

Option B seems like a good early trigger too since getting different equipment before installation hints at upcoming space issues. It’s an early sign before any delays or quality problems pop up.

0
AX
Andrew X.
2026-01-28

A. Sharing space with other machinery is an early indicator before actual installation problems show up, while the other options are more about issues after work has begun.

0
MO
Mason O.
2026-01-25

Maybe B, because getting the wrong equipment early can warn about space issues ahead.

0
AX
Ali X.
2026-01-18

It’s B too, since receiving different equipment early can reveal space problems before installation.

0
PL
Paul L.
2026-01-18

A/C? A hints at early warning by showing space constraints before installation. C and D feel more like problems after the risk has materialized, not early triggers. B could be early too but less direct than A.

0
PL
Paul L.
2026-01-17

Option B could also be an early risk trigger here. Getting a different type of equipment before installation might indicate the planned air conditioners won’t fit properly, signaling a space issue ahead of time. It’s more of a heads-up compared to delays or quality problems, which happen after installation begins. So B serves as an early warning that something might go wrong with space allocation.

0
US
User
2026-01-15

This one’s tricky, but I think it’s option A. Sharing space with other machinery sounds like an early warning sign before problems actually show up. A.

0