Question No. 13
During a project's initial planning session, the project team identifies a possible risk. The team is
under the impression that a critical vendor might delay delivery. This could impact both the project
schedule and budget. The team shares insights on the risk's likelihood and impact with the risk
manager.
What should the risk manager do?
Select one option, then reveal solution.
US
NZ
Naveed Z.
2026-02-22

Good point on getting vendor info, but D still fits best for timely risk assessment. D

0
SH
Shoaib H.
2026-02-10

D, assessing now helps prioritize instead of guessing or delaying action.

0
WA
Will A.
2026-01-27

It’s D because assessing risk early avoids surprises, no need to wait on vendor info.

0
SA
Sohail A.
2026-01-21

It’s D—waiting isn’t practical; assessing risk early helps prioritize.

0
SA
Sohail A.
2026-01-18

D seems right here since assessing the risk properly before taking action makes sense. But is it really best to wait for vendor updates first?

0