Free PMI PMI-RMP Actual Exam Questions - Question 10 Discussion

Question No. 10
During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact
their team. The stakeholder insists that this particular risk should be
mitigated to the greatest extent possible, however, the majority of other stakeholders feel that
different risks have higher probabilities of occurring.
Which action should the risk manager take to address this risk?
Select one option, then reveal solution.
US
MT
Mark T.
2026-02-17

Good point on logging it, but since the stakeholder is worried, I'd say escalate it—C.

0
OP
Osama P.
2026-01-16

I get why adding it to the register (D) makes sense, but wouldn't ignoring the stakeholder’s concern risk losing their buy-in? Shouldn’t the risk manager balance both impact severity and probability first?

0
OP
Osama P.
2026-01-16

Maybe D, just add it to the register and analyze later.

0