Question No. 7
A project team delivers a solution based on the approved requirements and is confident that it meets
the defined acceptance criteria.
What should the business analyst do to obtain signoff?
Select one option, then reveal solution.
US
OV
Osama V.
2026-02-16

Option A could work if the sponsor is explicitly the signoff authority, but without checking roles first, it’s risky to assume. Better to confirm via the RACI matrix to avoid mistakes.

0
OV
Osama V.
2026-02-15

Totally agree that just picking a stakeholder like in B might miss the actual signoff authority. D is safer since the RACI matrix clarifies roles and responsibilities for signoff. D.

0
OV
Osama V.
2026-02-14

B/D? B points to a specific stakeholder, but D ensures the official signoff authority.

0
MG
Mohammad G.
2026-01-17

D imo, checking the RACI matrix is the logical step to find out who signs off.