Question No. 9
Which of the following is developed from the project scope baseline and defines only that portion of
the project scope that is to be included within a related contract?
Select one option, then reveal solution.
US
OB
Osama B.
2026-02-19

It’s B because the procurement statement of work is specifically designed to pull the relevant scope from the baseline for contracts. The WBS covers everything, so it’s too broad here.

0
OB
Osama B.
2026-01-31

It’s B because the procurement statement of work is all about specifying the exact scope tied to a contract, unlike the WBS which covers the whole project.

0
OB
Osama B.
2026-01-22

Option B, the procurement statement of work, fits since it focuses on scope within contracts.