Dumps Box (DumpsBox) offers up-to-date practice exam questions for 1Z0-511 certification exam which are developed and validated by Oracle subject domain experts certified in Oracle 1Z0-511 . These practice questions are update regularly as we keep an eye on any recent changes in 1Z0-511 syllabus, and when there is update our team quickly adjusts the questions. This commitment to providing the best quality exam prep material to certification aspirants is what makes DumpsBox.com the best certification exam prep website. On top of that, our strong, yet strictly moderated, community based feedback keeps the content clean and current. Each question has helpful community discussion that provides it extra perspective and introduces helpful resources for better exam preparation. This also saves students from other outdated practice questions or illicit exam dumps that can have adverse affects on career. Browse through our Oracle 1Z0-511 exam questions and pass your exam on first try.

Question No. 1
You are setting up an AutoAccounting rule and trying to use "Class Code" as the parameter for that
rule. Which setup must exist in order to use "Class Code" as one of the parameters?
Select one option, then reveal solution.
Question No. 2
Which statement is true about the use of the calendar assigned to a project?
Select one option, then reveal solution.
Question No. 3
Refer to the exhibit.
1Z0-511 practice exam questions
In your company's Expenditure/Event Organization Hierarchy, organization labor costing rules are
assigned to all organizations except San Jose. What happens when you run the "PRC: Distribute labor
costs" program for a timecard transaction entered by an employee from the San Jose organization?
Select one option, then reveal solution.
Question No. 4
A project has been mistakenly set up as a capital project, instead of a contract project. The project
has already incurred expenditure. How can this be remedied?
Select one option, then reveal solution.
Question No. 5
Which project class type can include revenue budgets?
Select one option, then reveal solution.
Question No. 6
A company has multi-currency projects and tasks. What is the hierarchy in which the currency
attributes are allocated to a transaction?
Select one option, then reveal solution.
Question No. 7
A customer is billed using deliverable billing events, which are currently approved by the customer
and the finance director before invoicing. There are often invoices awaiting the finance director's
approval and release. The Finance director would like to use functionality that allows all invoices to
be approved and released automatically. How can this be achieved?
Select one option, then reveal solution.
Question No. 8
After receiving supplier costs from the Oracle Payables Supplier Invoices transaction source
vow
customer wants to perform adjustments in Oracle Projects. Which three setups should exist?
Select all that apply, then reveal solution.
Question No. 9
Which two options are not task attributes for financial task structure?
Select all that apply, then reveal solution.
Question No. 10
You have defined a Non-Labor resource "Mini Truck" with an expenditure type "Vehicle" that has a
rate of $100. This resource is attached to three Non-Labor resource organizations: "Construction-
East," "Construction-West," and "Construction-Central."
How do you set up a rate of $150 for usage charges when the "Mini Truck" owned by "Construction-
Central" is charged to a project?
Select one option, then reveal solution.
Question No. 11
A customer wants to make a new classification mandatory on all their new projects. Select the three
options that could help them accomplish this.
Select one option, then reveal solution.
Question No. 12
A new contract project is created for work for a customer by using event-based billing. A decision has
been made to give a discount to the customer on a particular invoice. You want to apply this discount
and reduce the invoice without affecting revenue. Which event type should be used to achieve this?
Select one option, then reveal solution.
Question No. 13
You have imported Labor transactions into Oracle Projects from Oracle Time and Labor by running
the "PRC: Transaction Import" program. What is the correct sequence to run the concurrent
programs listed below to transfer the cost and accounting entries of these transactions to General
Ledger?
1. PRC: Distribute Labor Cost
2.PRC: Transfer Journal Entries to GL
3.PRC: Create Accounting (with the Transfer to GL option set to "No")
4.PRC: Interface Labor Costs to GL
5.PRC: Generate Cost Accounting Events
6.PRC: Distribute and Interface tabor costs to GL
Select one option, then reveal solution.
Question No. 14
A company requires advance payments for their contract projects. How would they ensure that for
specific types of work they always have an advance payment?
Select one option, then reveal solution.
Question No. 15
A client requires a project definition that allows for charging expenditures to the project at a higher
Work Breakdown Structure level than where the manually entered percentage complete progress is
captured. Which three Shared Structure relationships will support this requirement?
Select all that apply, then reveal solution.