Question No. 2
In an organization's feasibility study to acquire hardware to support a new web server,
omission of which of the following would be of MOST concern?
Select one option, then reveal solution.
US
AU
Amir U.
2026-02-22

Not B, the financial stability of vendors matters but isn't as critical as knowing if the hardware is worth buying in the first place, so D still seems more crucial.

0
NI
Naveed I.
2026-02-18

D imo, because without cost-benefit, you can’t justify the purchase itself.

0
MT
Marco T.
2026-01-21

B imo, because if the vendor isn’t financially stable, they might go under mid-project or fail to provide support later. That risk can sink the whole acquisition regardless of cost or reputation.

0
MT
Marco T.
2026-01-15

Maybe D makes the most sense since cost-benefit analysis directly impacts the decision to buy. But I’m wondering if the question assumes a specific scope for the feasibility study? Like, is it just about hardware specs or the vendor relationship too? Without knowing that, it’s hard to say which omission is most critical. Anyone else think vendor financial stability (B) might matter more if the study’s long-term focused?

0