Home/aace international/Free AACE International PSP Actual Exam Questions

Free AACE International PSP Actual Exam Questions

The questions for this exam were last updated on January 7, 2026

Dumps Box (DumpsBox) offers up-to-date practice exam questions for PSP certification exam which are developed and validated by AACE international subject domain experts certified in AACE International PSP . These practice questions are update regularly as we keep an eye on any recent changes in PSP syllabus, and when there is update our team quickly adjusts the questions. This commitment to providing the best quality exam prep material to certification aspirants is what makes DumpsBox.com the best certification exam prep website. On top of that, our strong, yet strictly moderated, community based feedback keeps the content clean and current. Each question has helpful community discussion that provides it extra perspective and introduces helpful resources for better exam preparation. This also saves students from other outdated practice questions or illicit exam dumps that can have adverse affects on career. Browse through our AACE International PSP exam questions and pass your exam on first try.

Question No. 1
When are KPIs defined?
Select one option, then reveal solution.
Question No. 2
Identify the minimum project duration.
PSP practice exam questions
Select one option, then reveal solution.
Question No. 3
In a "crashed" schedule, which is a chain of activities that precede activity 2004?
PSP practice exam questions
Select one option, then reveal solution.
Question No. 4
By subtracting a measured unit productivity rate during an impacted period from the unit
productivity rate during an unimpacted period, the resulting value represents:
Select one option, then reveal solution.
Question No. 5
Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is
indicated?
Select one option, then reveal solution.
Question No. 6
What is the cycle time?
PSP practice exam questions
Select one option, then reveal solution.
Question No. 7
What defines a KPI?
Select one option, then reveal solution.
Question No. 8
How many workdays occur from the start of the Product Testing to the Product Available milestone?
Select one option, then reveal solution.
Question No. 9
In order for a claimant to be entitled to an extension of contract time for a delay event (and further
to be considered compensable):
Select one option, then reveal solution.
Question No. 10
Determine the driving activity for Activity 10001.
PSP practice exam questions
Select one option, then reveal solution.
Question No. 11
The addition of which of the following relationships would cause a logic loop?
Select one option, then reveal solution.
Question No. 12
Which of the following options is NOT a feasible method to reduce the overall completion time of the
toll road program?
Select one option, then reveal solution.
Question No. 13
Why does activity 11001 not show successor activities?
PSP practice exam questions
Select one option, then reveal solution.
Question No. 14
At a minimum, periodic reporting must be done at what interval?
Select one option, then reveal solution.
Question No. 15
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts
each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned
working duration for this work?
PSP practice exam questions
Select one option, then reveal solution.